Thursday, December 1, 2022

November 30 2022

                                                 Daily Job Report


Fincon -  4 Worker's

Work on framing & backing, hang doors, move material & clean up.

Capitol Glass - 4 Worker's

Work on east building, east wall frames & clean up

Horizon Plumbing - 2 Worker's

Work on plumbing on west T.I. & clean up

Pro Heating & Air    -  2 Workers

Install duct work on east build-out, work on duct on west T.I. & east T.I., layout unload material & clean up

Canvis Drywall  -  8 Workers

Work on hanging sheetrock from north to south & unload material & clean up

UIS Paint - 1 Worker

Work on Bldg c exterior walls & clean up

Advanced Roofing - 2 Worker's

Truck in roof cap material & unload & clean up


Kimco - 2 Worker's

Work on fire lines in east T.I. & clean up


            Weather - Sunny & Cold - High 36  Low 18