Wednesday, June 2, 2021

June 1 2021

  Daily Job Report


Fincon - 4 Worker's

Work on mobilizing, loading & moving material, straighten out conex's, unload rebar, layout & clean up.

 

Esp Excavation - 2 Worker's

 Work on cutting & filling grades, work on grading out east building pad & clean up


           Weather - Partly Cloudy - High 84  Low 45






No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...