Wednesday, June 2, 2021

June 2 2021

 Daily Job Report


Fincon - 4 Worker's

Work on mobilizing, loading & moving material, straighten out conex's, unload rebar, layout & clean up.

 

Esp Excavation - 3 Worker's

 Work on cutting & filling grades, work on grading out east building pad & clean up


           Weather - Sunny & Hot - High 89  Low 48









No comments:

Post a Comment

December 13 2022