Tuesday, July 27, 2021

July 26 2021

      Daily Job Report


Fincon - 6 Worker's

Finish setting the floor forms on building B, start on floor rebar, layout & clean up.

 

Esp Excavation - 3 Worker's

Dig trenches for plumbers on building C water & clean up

Horizon Plumbing - 2 Worker's

Work on the layout of sewer and industrial waste line building C, unload material & clean up


                   Weather - Sunny - High 101  Low 67