Tuesday, July 27, 2021

July 27 2021

     Daily Job Report


Fincon - 7 Worker's

Work on the floor rebar building B, layout & clean up.

 

Esp Excavation - 3 Worker's

Finish trenches for plumbers on building C, bed with pea gravel water & clean up

Horizon Plumbing - 2 Worker's

Cut and cap all pipes on building B, unload material, start on industrial waste line on building C & clean up


                   Weather - Sunny - High 99  Low 67
















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...