Daily Job Report
Fincon - 8 Workers
Work on panels for Building B, layout, install bolts for the top plate, work on the chamfer, get the equipment ready for floor pour, and clean up.
Work on panels for Building B, layout, install bolts for the top plate, work on the chamfer, get the equipment ready for floor pour, and clean up.
Weather - Sunny & Hazy - High 86 Low 55








No comments:
Post a Comment