              Daily Job Report


Fincon - 10 Worker's

Strip wall panels on bldg B, work on forms, ravel, chamfer, and bond breaker east side of building C, layout & clean up.

 

Harris Rebar- 6 Worker's

Work on jambs and west panels for bldg C & clean up


      Weather - Partly Cloudy - High 52  Low 26