Tuesday, November 23, 2021

November 23 2021

               Daily Job Report


Fincon - 10 Worker's

Strip wall panels on bldg B, work on forms, ravel, chamfer, and bond breaker east side of building C, layout & clean up.

 

Harris Rebar- 6 Worker's

Work on jambs and west panels for bldg C & clean up


      Weather - Mostly Sunny - High 53  Low 26








No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...