Daily Job Report
Fincon - 15 Worker's
Pour & finish 15 wall panels on bldg B north & east side, clean out panels, move material & organize, work on forms of remaining bldg B panels, strip forms, layout & clean up.
Pour & finish 15 wall panels on bldg B north & east side, clean out panels, move material & organize, work on forms of remaining bldg B panels, strip forms, layout & clean up.
Harris Rebar- 8 Worker's
Work on 2nd top mat in wall panels building B south side, start bottom bar on remaining panels & clean up
Work on 2nd top mat in wall panels building B south side, start bottom bar on remaining panels & clean up