Wednesday, November 17, 2021

November 16 2021

           Daily Job Report


Fincon - 11 Worker's

Strip wall panels on bldg B west side, clean out panels, install weld plates and lifting hardware, move material & organize, work on forms for both buildings, layout & clean up.

 

Harris Rebar- 8 Worker's

Work on 2nd top mat in wall panels building B south side, work on bottom mat remaining 6 panels & clean up


      Weather - Cloudy - High 54  Low 32





No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...