Wednesday, November 17, 2021

November 17 2021

            Daily Job Report


Fincon - 11 Worker's

Strip wall panels on bldg B west side, clean out panels, install weld plates and lifting hardware, move material & organize, work on forms for both buildings, layout & clean up.

 

Harris Rebar- 8 Worker's

Work on the bottom mat in remaining 6 panels on bldg B & clean up


      Weather - Sunny & Cold - High 41  Low 26