Tuesday, November 2, 2021

November 2 2018

           Daily Job Report


Fincon - 8 Worker's

Finish up panels on building B for pour & work on wall panel forms on bldg C, rip down forms for bldg C, unload material & clean up.

Inspect face rebar on remaining panels

 

Harris Rebar- 8 Worker's

Work on upper mats on bldg B west side & clean up


        Weather - Cloudy Rain - High 57  Low 37