Thursday, November 4, 2021

November 3 2021

         Daily Job Report


Fincon - 15 Worker's

Pour & install foam in 15 wall panel forms on bldg B north & east side, clean out panels, move material & organize, work on forms of bldg C panels, layout &clean up.

 

Harris Rebar- 8 Worker's

Work on 2nd top mat in wall panels building B west side & clean up


      Weather - Sunny - High 54  Low 30












No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...