Thursday, November 4, 2021

November 4 2021

            Daily Job Report


Fincon - 9 Worker's

Finish up panels on building B for pour & work on wall panel forms on bldg C, rip down forms for bldg C, unload material & clean up.

Inspect upper rebar on southwest panels

 

Harris Rebar- 10 Worker's

Work on upper mats on bldg B west side, unload rebar & clean up


        Weather - Sunny - High 57  Low 37