Monday, November 8, 2021

November 8 2021

             Daily Job Report


Fincon - 9 Worker's

Work on remainig panels on building B & work on wall panel lifters and brace inserts west side, rip down forms, unload material & clean up.



 

Harris Rebar- 10 Worker's

Work on upper mats on bldg B east side, unload rebar & clean up


        Weather - Cloudy & Cool - High 57  Low 31






No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...