Wednesday, November 10, 2021

November 9 2021

              Daily Job Report


Fincon - 9 Worker's

Work on remaining panels on building B & work on wall panel lifters, weld plates and brace inserts west side, rip down forms, unload material & clean up.



 

Harris Rebar- 10 Worker's

Work on upper mats on bldg B east side, unload rebar & clean up


        Weather - Cloudy & Rain - High 42  Low 31