Daily Job Report
Fincon - 10 Worker's
Work on forms, ravel, chamfer, and bond breaker east side of building C, bring in frost & snow protection, layout, strip & load forms from Building C & clean up.
Work on forms, ravel, chamfer, and bond breaker east side of building C, bring in frost & snow protection, layout, strip & load forms from Building C & clean up.
Harris Rebar- 4 Worker's
Work on jambs & rebar for bldg C east side panels & clean up
Work on jambs & rebar for bldg C east side panels & clean up
ESP Excavation- 4 Worker's
Haul in equipment, start on west side footings of building B, haul off material & clean up
Haul in equipment, start on west side footings of building B, haul off material & clean up