Friday, December 10, 2021

December 9 2021

                  Daily Job Report


Fincon - 4 Worker's

Work on forms, bring in frost & snow protection, layout, strip & load forms & clean up.

 

Harris Rebar- 4 Worker's

Work on jambs & rebar for bldg C east side panels & clean up

ESP Excavation- 4 Worker's

Work on west & south side footings of building B, haul off material & clean up

      Weather - Snow All Day - High 33  Low 26








No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...