Wednesday, January 12, 2022

January 12 2022

                               Daily Job Report


Fincon -  14 Worker's

Work on uncovering & covering frost & snow protection, form and install rebar in bldg B footings, install lifting hardware, move & organize footing boards, clean off weld plates on bldg B, strip poured panels on bldg C, layout & clean up.


 Weather - Sunny - High 39   Low 18