Daily Job Report
Fincon - 18 Worker's
Work on uncovering & covering frost & snow protection, pour & finish 10 panels, work on bldg B footings, tie rebar, move & organize material, strip forms & clean up.
Harris Rebar- 6 Worker's
Work on uncovering & covering frost & snow protection, pour & finish 10 panels, work on bldg B footings, tie rebar, move & organize material, strip forms & clean up.
Harris Rebar- 6 Worker's
Work on jambs & rebar for bldg C side upper mat panels & clean up
Work on jambs & rebar for bldg C side upper mat panels & clean up