Friday, January 7, 2022

January 7 2022

                             Daily Job Report


Fincon -  12 Worker's

Work on uncovering & covering frost & snow protection, form and install rebar in bldg B footings , install lifting hardware, move & organize footing boards, strip poured panels on bldg C, layout & clean up.

 Harris Rebar- 7 Worker's

Work on jambs & rebar for bldg C east side upper mat panels & clean up


 Weather - Sunny - High 51  Low 34









No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...