Monday, January 10, 2022

January 10 2022

                              Daily Job Report


Fincon -  12 Worker's

Work on uncovering & covering frost & snow protection, form and install rebar in bldg B footings , install lifting hardware, move & organize footing boards, strip poured panels on bldg C, layout & clean up.

 Harris Rebar- 4 Worker's

Work on jambs & rebar for bldg C east side upper mat panels & clean up


 Weather - Sunny - High 39   Low 18