Thursday, March 17, 2022

March 16 2022

                                             Daily Job Report


Fincon -  12 Worker's

Work on footings for dock walls, finish stripping panels with 2' windows, weld panel corners on building C, finish removing stiff backs, clean floors & clean up.

 ESP Excavation - 3 Worker's

Work on  cutting & grading on building C layout & clean up

 Wasatch  - 6 Worker's
Hang iron on building B north end. work on sorting out decking, columns, and joists for roofs

Pink Towers 1 Worker
Work on grinding building C


 Weather -  Rain, Wind, Colder  - High 38   Low 30











No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...