Thursday, March 17, 2022

March 17 2022

                                             Daily Job Report


Fincon -  10 Worker's

Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, clean floors & clean up.

 ESP Excavation - 2 Worker's

Work on  cutting & grading on building C layout & clean up

 Wasatch  - 6 Worker's
Hang iron on building B north to south. work on sorting out decking, columns, and joists for roofs

Pink Towers 1 Worker
Work on grinding building C


 Weather -  Sunny  - High 48   Low 32