Monday, March 21, 2022

March 21 2022

                            Daily Job Report


Fincon -  13 Worker's

Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, clean floors & clean up.

 ESP Excavation - 4 Worker's

Work on dock footings & setting sewer lift station, layout & clean up

 Wasatch  - 6 Worker's
Hang iron on building B north to south. work on sorting out decking, columns, and joists for roofs

All Cuts - 4 Worker's
Work on core drilling for roof drains, 20 - 8" Holes


 Weather -  Sunny, Windy  - High 46   Low 30