Daily Job Report
Fincon - 11 Worker's
Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, clean floors & clean up.
Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, clean floors & clean up.
ESP Excavation - 4 Worker's
ESP Excavation - 4 Worker's
Work on sewer main & sewer lift station, layout & clean up
Work on sewer main & sewer lift station, layout & clean up
Wasatch - 4 Worker'sHang iron on building B north to south. work on sorting out decking, columns, and joists for roofs
All Cuts - 4 Worker'sFinish core drilling for roof drains, 20 - 8" Holes
Wasatch - 4 Worker's
Hang iron on building B north to south. work on sorting out decking, columns, and joists for roofs
All Cuts - 4 Worker's
Finish core drilling for roof drains, 20 - 8" Holes