Thursday, March 24, 2022

March 23 2022

                              Daily Job Report


Fincon -  12 Worker's

Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, clean floors & clean up.

 ESP Excavation - 4 Worker's

Work on sewer main & finish setting sewer lift station, layout & clean up

 Wasatch  - 4 Worker's
Finish iron on building B. work on bracing & angels, weld up remaining joists



 Weather -  Sunny  - High 56   Low 31