Daily Job Report
Fincon - 12 Worker's
Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, clean floors & clean up.
Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, clean floors & clean up.
ESP Excavation - 4 Worker's
ESP Excavation - 4 Worker's
Work on sewer main & finish setting sewer lift station, layout & clean up
Work on sewer main & finish setting sewer lift station, layout & clean up
Wasatch - 4 Worker'sFinish iron on building B. work on bracing & angels, weld up remaining joists
Wasatch - 4 Worker's
Finish iron on building B. work on bracing & angels, weld up remaining joists