Daily Job Report
Fincon - 16 Worker's
Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, start dock walls on bldg c, clean floors & clean up.
Work on footings for dock walls, work on patching building B, weld panel corners & lap panels, start dock walls on bldg c, clean floors & clean up.
ESP Excavation - 4 Worker's
ESP Excavation - 4 Worker's
Work on sewer main east side & backfill & compact center main, layout & clean up
Work on sewer main east side & backfill & compact center main, layout & clean up
Wasatch - 4 Worker'sWork on bracing & angels, install roof frame drains & clean up
Wasatch - 4 Worker's
Work on bracing & angels, install roof frame drains & clean up