March 28 2022

                                 Daily Job Report


Fincon -  17 Worker's

Pour footings & 5 dock walls on bldg c, work on patching building B, weld panel corners & lap panels, clean floors & clean up.

 Wasatch  - 4 Worker's
Work on bracing & angels, install roof frame drains & clean up



 Weather -  Cloudy  - High 48   Low 34