                                           Daily Job Report


Fincon -  11 Worker's

Work on removing braces & bundling,  from blg B, clean dock wall forms, work on patching building B, pour in columns on bldg B, clean & cut floor joints on bldg B, layout & clean up.

 Wasatch  - 6 Worker's
Work on finishing up decking on bldg B, work on setting joist's on Bldg B, clean up

ESP Excavation - 4 Worker's

Work on sewer laterals to the dock side, backfill & compact, layout & clean up


            Weather -  Cloudy, Cold Snow   - High 41   Low 24