Daily Job Report
Fincon - 11 Worker's
Start removing braces from blg B, move dock wall forms to clean, work on patching building B, finish rebar on dock leveler walls, clean & cut floor joints on bldg B, layout & clean up.
Start removing braces from blg B, move dock wall forms to clean, work on patching building B, finish rebar on dock leveler walls, clean & cut floor joints on bldg B, layout & clean up.
Wasatch - 6 Worker'sWork on finishing up decking on bldg B, work on setting joist's on Bldg B, clean up
Wasatch - 6 Worker's
Work on finishing up decking on bldg B, work on setting joist's on Bldg B, clean up
ESP Excavation - 4 Worker's
ESP Excavation - 4 Worker's
Work on sewer laterals to the dock side, backfill & compact, layout & clean up
Work on sewer laterals to the dock side, backfill & compact, layout & clean up