Daily Job Report
Fincon - 8 Worker's
Work on patching building B, finish cuting floor joints on bldg B, work on dock extensions on bldg B, clean up.
Work on patching building B, finish cuting floor joints on bldg B, work on dock extensions on bldg B, clean up.
Wasatch - 4 Worker'sWork on bridging & misc welding on Bldg c, clean up
Wasatch - 4 Worker's
Work on bridging & misc welding on Bldg c, clean up
ESP Excavation - 4 Worker's
ESP Excavation - 4 Worker's
Work on south storm drain box's & lines, compact, layout & clean up
Work on south storm drain box's & lines, compact, layout & clean up
Advanced Roofing - 4 Worker's
Advanced Roofing - 4 Worker's
Finish the south half of bldg B & start on north side of the roof, layout & clean up
Finish the south half of bldg B & start on north side of the roof, layout & clean up