Friday, April 22, 2022

April 21 2022

                                              Daily Job Report


Fincon -  8 Worker's

Work on patching building B, finish cuting floor joints on bldg B, work on weld plates, layout & work on dock extensions on bldg B, clean up.

 Wasatch  - 4 Worker's
Work on bridging & decking on Bldg c, clean up

ESP Excavation - 4 Worker's

Work on storm drain box's & lines, compact, layout & clean up

Highmark Elec - 4 Worker's

Work on electrical lines in pourbacks, layout & clean up

         Weather -  Partly Sunny & Windy  - High 74  Low 43













No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...