Wednesday, May 11, 2022

May 11 2022

                                      Daily Job Report


Fincon -  12 Worker's

Work on interioer patching building B, work on overhead doors, work on dock steel, layout & clean up.

 Wasatch  - 4 Worker's
Work on bridging & misc welding on Bldg c, clean up

ESP Excavation - 3 Worker's

Work on dock drains & backfill pourbacks building B, compact, layout & clean up

Advanced Roofing - 6 Worker's

Work on building b north end, layout, haul over material & clean up


            Weather -  Sunny  - High 70  Low 38