Tuesday, May 17, 2022

May 12 2022

                       Daily Job Report


Fincon -  12 Worker's

Work on interior patching building B, work on overhead doors, work on dock steel & forming the pits, layout & clean up.

 Wasatch  - 4 Worker's
Work on decking & misc welding on Bldg c, clean up

ESP Excavation - 3 Worker's

Work on dock drains & backfill pourbacks building B, compact, layout & clean up

Advanced Roofing - 6 Worker's

Work on building b north end, layout, haul over material & clean up


            Weather -  Sunny  - High 70  Low 38












No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...