Wednesday, June 15, 2022

June 13 2022

      Daily Job Report


Fincon -  9 Worker's

Pour & finish pourbacks east side Bldg C , work on capping weld plates building B, install rebar in pourbacks, go over for final patch on building B, clean floors & saw cut

ESP Excavation - 4 Worker's
Work on water mains down center of buildings, backfill, compact, layout, haul off material & clean up

Horizon Plumbing - 2 Worker's

Work on cleanouts & hose bibs, water lines & clean up


Advanced Roofing - 6 Worker's

Work on roof bldg C, move material, layout & clean up

UIS Painting  - 2 Worker's

Work on base coat bldg B

            Weather -  Rain & cloudy - High 70  Low 51








No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...