       Daily Job Report


Fincon -  9 Worker's

Work on pourbacks west side Bldg C , work on capping weld plates building B, install rebar in pourbacks, final patch on building B, start layout on buildout of bldg C, clean floors & saw cut

ESP Excavation - 4 Worker's
Work on water mains down center of buildings, backfill, compact, layout, haul off material & clean up

Horizon Plumbing - 2 Worker's

Work on cleanouts & hose bibs, water lines & clean up

Advanced Roofing - 6 Worker's

 Work on finishing up bldg C roof

UIS Painting - 4 Worker's

 Work on finishing up base coat on Bldg B