Friday, June 24, 2022

June 17 2022

       Daily Job Report


Fincon -  12 Worker's

Strip pourbacks west side Bldg C , work on capping weld plates, install rebar in pourbacks, final patch on building B, work on layout on buildout of bldg C, clean floors & saw cut

ESP Excavation - 4 Worker's
Work on water mains east of buildings C, backfill, compact, layout, haul off material & clean up


UIS Painting - 3 Worker's

 Work on interior Bldg B around 2' windows


            Weather -  Sunny - High 91  Low 48