Daily Job Report
Fincon - 12 Worker's
Strip pourbacks west side Bldg C , work on capping weld plates, install rebar in pourbacks, final patch on building B, work on layout on buildout of bldg C, clean floors & saw cut
Strip pourbacks west side Bldg C , work on capping weld plates, install rebar in pourbacks, final patch on building B, work on layout on buildout of bldg C, clean floors & saw cut
ESP Excavation - 4 Worker'sWork on water mains east of buildings C, backfill, compact, layout, haul off material & clean up
ESP Excavation - 4 Worker's
Work on water mains east of buildings C, backfill, compact, layout, haul off material & clean up
Horizon Plumbing - 2 Worker's
Horizon Plumbing - 2 Worker's
Work on cleanouts & hose bibs, water lines & clean up
Work on cleanouts & hose bibs, water lines & clean up
UIS Painting - 3 Worker's
UIS Painting - 3 Worker's
Work on interior Bldg B around 2' windows
Work on interior Bldg B around 2' windows
Steerling Structures - 3 Worker's
Steerling Structures - 3 Worker's
Frame interior bathroom & fire riser room Bldg B, clean up
Frame interior bathroom & fire riser room Bldg B, clean up
Weather - Sunny - High 91 Low 48
Weather - Sunny - High 91 Low 48