Wednesday, June 8, 2022

June 3 2022

  Daily Job Report


Fincon -  14 Worker's

Work on pourbacks west & south side Bldg C , work on overhead doors bldg C, install rebar in pourbacks, install bulkheads, work on dock pits bldg C, patch floor on bldg C, layout & clean up.

U.I.S Paint - 2 Worker's

Work on bldg B East wall & clean up

ESP Excavation - 4 Worker's

Work on water mains, layout & clean up

Highmark Elec - 1 Worker's

Work on conduit in roof building B, layout & clean up

Advanced Roofing - 6 Worker's

Work on roof bldg C, move material, layout & clean up


            Weather -  Sunny - High 82  Low 49