Thursday, June 2, 2022

June 2 2022

                            Daily Job Report


Fincon -  14 Worker's

Pour & finish pourbacks west & south side Bldg B, work on overhead doors bldg C, install rebar in pourbacks, install bulkheads, work on dock pits bldg C, patch floor on bldg C, layout & clean up.

U.I.S Paint - 2 Worker's

Work on bldg B East & west wall & clean up

ESP Excavation - 4 Worker's

Work on water mains, pour kickers, layout & clean up

Highmark Elec - 1 Worker's

Work on conduit in roof building B, layout & clean up

Horizon Plumbing - 2 Worker's

Work on roof drains bldg C, layout & clean up

Advanced Roofing - 6 Worker's

Start on roof bldg C, move material, layout & clean up


            Weather -  Sunny - High 82  Low 49

















No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...