Daily Job Report
Fincon - 14 Worker's
Work on pourbacks west & south side Bldg C , work on overhead doors bldg C, install rebar in pourbacks, install bulkheads, work on dock pits bldg C, patch floor on bldg C, layout & clean up.
U.I.S Paint - 2 Worker's
Work on pourbacks west & south side Bldg C , work on overhead doors bldg C, install rebar in pourbacks, install bulkheads, work on dock pits bldg C, patch floor on bldg C, layout & clean up.
U.I.S Paint - 2 Worker's
Work on bldg B East wall & clean up
Work on bldg B East wall & clean up
ESP Excavation - 4 Worker's
ESP Excavation - 4 Worker's
Work on water mains, layout & clean up
Work on water mains, layout & clean up
Horizon Plumbing - 2 Worker's
Horizon Plumbing - 2 Worker's
Finish roof drains bldg C, layout & clean up
Finish roof drains bldg C, layout & clean up
Advanced Roofing - 6 Worker's
Advanced Roofing - 6 Worker's
Work on roof bldg C, move material, layout & clean up
Work on roof bldg C, move material, layout & clean up