Daily Job Report
Fincon - 10 Worker's
Work on pourbacks Bldg C , pour & finish remaning dock pit floors bldg C, install rebar in pourbacks, install bulkheads, patch bldg B south walls, layout & clean up.
Work on pourbacks Bldg C , pour & finish remaning dock pit floors bldg C, install rebar in pourbacks, install bulkheads, patch bldg B south walls, layout & clean up.
Wasatch Erection - 2 Worker's
Wasatch Erection - 2 Worker's
Work on torquing bolts in cross bracing both buildings & clean up
Work on torquing bolts in cross bracing both buildings & clean up
U.I.S Paint - 2 Worker's
U.I.S Paint - 2 Worker's
Work on washing bldg C & clean up
Work on washing bldg C & clean up
ESP Excavation - 4 Worker's
ESP Excavation - 4 Worker's
Work on water mains, backfill & compact, layout & clean up
Work on water mains, backfill & compact, layout & clean up
Horizon Plumbing - 2 Worker's
Horizon Plumbing - 2 Worker's
Work on hose bibs & plumbing lines, layout & clean up
Work on hose bibs & plumbing lines, layout & clean up
Advanced Roofing - 6 Worker's
Advanced Roofing - 6 Worker's
Work on roof , move material, layout & clean up
Work on roof , move material, layout & clean up