Thursday, June 9, 2022

June 9 2022

     Daily Job Report


Fincon -  9 Worker's

Pour & finish pourbacks north & east side Bldg C , work on capping weld plates building B, install rebar in pourbacks, go over for final patch on building B, clean floors & saw cut

ESP Excavation - 4 Worker's
Work on water mains down center of buildings, backfill, compact, layout, haul off material & clean up

Horizon Plumbing - 2 Worker's

Work on cleanouts & hose bibs, start water lines & clean up

Highmark Elec - 1 Worker's

Work on conduit in pourback building C, layout & clean up

Advanced Roofing - 6 Worker's

Work on roof bldg C, move material, layout & clean up


            Weather -  Sunny - High 90  Low 61










No comments:

Post a Comment

December 13 2022

                                    Daily Job Report Fincon  -  4 Worker's Hang door frames in the west buildout, work on floors in east...