Daily Job Report
Fincon - 9 Worker's
Pour & finish pourbacks north & east side Bldg C , work on capping weld plates building B, install rebar in pourbacks, go over for final patch on building B, clean floors & saw cut
Pour & finish pourbacks north & east side Bldg C , work on capping weld plates building B, install rebar in pourbacks, go over for final patch on building B, clean floors & saw cut
ESP Excavation - 4 Worker'sWork on water mains down center of buildings, backfill, compact, layout, haul off material & clean up
ESP Excavation - 4 Worker's
Work on water mains down center of buildings, backfill, compact, layout, haul off material & clean up
Horizon Plumbing - 2 Worker's
Horizon Plumbing - 2 Worker's
Work on cleanouts & hose bibs, start water lines & clean up
Work on cleanouts & hose bibs, start water lines & clean up
Highmark Elec - 1 Worker's
Highmark Elec - 1 Worker's
Work on conduit in pourback building C, layout & clean up
Work on conduit in pourback building C, layout & clean up
Advanced Roofing - 6 Worker's
Advanced Roofing - 6 Worker's
Work on roof bldg C, move material, layout & clean up
Work on roof bldg C, move material, layout & clean up