Daily Job Report
Fincon - 12 Worker's
Pour & finish concrete pourbacks Bldg B, work on overhead doors bldg C, pour & finish concrete east side of building B, install rebar in pourbacks, install bulkheads, patch floor on bldg C, layout & clean up.U.I.S Paint - 2 Worker's
Pour & finish concrete pourbacks Bldg B, work on overhead doors bldg C, pour & finish concrete east side of building B, install rebar in pourbacks, install bulkheads, patch floor on bldg C, layout & clean up.
U.I.S Paint - 2 Worker's
Work on bldg B north wall & clean up
Work on bldg B north wall & clean up
ESP Excavation - 2 Worker's
ESP Excavation - 2 Worker's
Work on water mains, layout & clean upHighmark Elec - 2 Worker's
Work on water mains, layout & clean up
Highmark Elec - 2 Worker's
Work on conduit in roof building B, layout & clean up
Horizon Plumbing - 2 Worker's
Work on conduit in roof building B, layout & clean up
Horizon Plumbing - 2 Worker's
Work on roof drains bldg C, layout & clean up
Work on roof drains bldg C, layout & clean up