June 1 2022

                           Daily Job Report


Fincon -  12 Worker's

Work on pourbacks west side Bldg B, work on overhead doors bldg C, install rebar in pourbacks, install bulkheads, work on dock pits bldg C, patch floor on bldg C, layout & clean up.

U.I.S Paint - 2 Worker's

Work on bldg B north & west wall & clean up

ESP Excavation - 2 Worker's

Work on water mains, layout & clean up

Highmark Elec - 2 Worker's

Work on conduit in roof building B, layout & clean
 up

Advanced Roofing - 2 Worker's

Start on bldg C moving material, layout & clean up


Horizon Plumbing - 2 Worker's

Work on roof drains bldg C, layout & clean up

            Weather -  Sunny - High 79  Low 48