Thursday, July 14, 2022

July 13 2022

                                       Daily Job Report


Fincon -  12 Worker's

Work on patching interior bldg B & building C, strip dumpster enclosures on bldg B, tie rebar, excavate & boackfill for plumbing drains on T.I., compact & clean up.

U.I.S Paint - 4 Worker's

Work on painting bldg B interior & clean up

Highmark Elec - 2 Worker's

Work on bldg B interior power, start layout of transformers & gear cabinet's & clean up

Horizon Plumbing - 2 Worker's

Work on water lines and drains in building C, layout & clean up

ESP Excavation - 3  workers

Start moving gas main on south end, move extra dirt, layout & clean up

Capitol Glass - 4 Worker's

Work on window frames in building B, layout & clean up

Kimco Fire - 2 Worker's

Work on fire lines in building B, unload material, layout & clean up

            Weather -  Sunny - High 102  Low 70