Daily Job Report
Fincon - 12 Worker's
Work on patching interior bldg B & building C, strip dumpster enclosures on bldg B, tie rebar, excavate & boackfill for plumbing drains on T.I., compact & clean up.
Work on patching interior bldg B & building C, strip dumpster enclosures on bldg B, tie rebar, excavate & boackfill for plumbing drains on T.I., compact & clean up.
U.I.S Paint - 4 Worker's
U.I.S Paint - 4 Worker's
Work on painting bldg B interior & clean up
Work on painting bldg B interior & clean up
Highmark Elec - 2 Worker's
Highmark Elec - 2 Worker's
Work on bldg B interior power, start layout of transformers & gear cabinet's & clean up
Work on bldg B interior power, start layout of transformers & gear cabinet's & clean up
Horizon Plumbing - 2 Worker's
Horizon Plumbing - 2 Worker's
Work on water lines and drains in building C, layout & clean up
Work on water lines and drains in building C, layout & clean up
ESP Excavation - 3 workers
ESP Excavation - 3 workers
Start moving gas main on south end, move extra dirt, layout & clean up
Start moving gas main on south end, move extra dirt, layout & clean up
Capitol Glass - 4 Worker's
Capitol Glass - 4 Worker's
Work on window frames in building B, layout & clean up
Work on window frames in building B, layout & clean up
Kimco Fire - 2 Worker's
Kimco Fire - 2 Worker's
Work on fire lines in building B, unload material, layout & clean up
Work on fire lines in building B, unload material, layout & clean up
Weather - Sunny - High 102 Low 70