Thursday, July 14, 2022

July 14 2022

                                        Daily Job Report


Fincon -  12 Worker's

Work on patching interior bldg B & building C, set east dumpster enclosures on bldg C, tie rebar & backfill for plumbing drains on T.I., compact & clean up.

U.I.S Paint - 2 Worker's

Work on painting bldg B interior & clean up

Highmark Elec - 1 Worker's

Work on bldg C interior power & clean up

Horizon Plumbing - 2 Worker's

Work on water lines and drains in building C, layout & clean up

ESP Excavation - 4  workers

Finish moving gas main on south end, bed with sand, move extra dirt, layout & clean up

Capitol Glass - 4 Worker's

Work on window frames in building B, layout & clean up

Kimco Fire - 2 Worker's

Work on fire lines in building B, unload material, layout & clean up

            Weather -  Cloudy  - High 90  Low 70