                                         Daily Job Report


Fincon -  12 Worker's

Work on patching interior bldg B & building C, set east dumpster enclosures on bldg C, tie rebar & backfill for plumbing drains on T.I., compact & clean up.

ESP Excavation - 3  workers

Backfill gas main & grade retention ponds, layout & clean up

U.I.S Paint - 2 Worker's

Work on painting bldg B interior & clean up

Highmark Elec - 1 Worker's

Work on bldg C & B interior power & clean up

Capitol Glass - 2 Worker's

Work on window frames in building B, layout & clean up

Kimco Fire - 2 Worker's

Work on fire lines in building B, unload material, layout & clean up

            Weather -  Sunny Hot - High 99  Low 70