July 19 2022

                                        Daily Job Report


Fincon -  12 Worker's

Work on patching interior bldg B & building C, pour & finish east dumpster enclosures on bldg C, set columns & headers on T.I., grade drain trenches compact & clean up.

U.I.S Paint - 2 Worker's

Work on painting bldg B interior & clean up

Highmark Elec - 2 Worker's

Work on bldg C & B interior power & clean up

Horizon Plumbing - 2 Worker's

Work on water lines and drains in building C & B, work on the underground in T.I. Bldg C, layout & clean up

ESP Excavation - 4  workers

Rough grade on west & north ponds, grade docks, move extra dirt, layout & clean up

Capitol Glass - 4 Worker's

Work on window frames in building B, layout & clean up

Kimco Fire - 2 Worker's

Work on fire lines in building B, unload material, layout & clean up

Industrial Door - 1 Worker

Work on overhead doors, load move & unload material, layout & clean up